Simprug Field · Integrated field development · Economic analysis

From field development
to investment decision.

An interactive case study of my role as an Economic Analyst in evaluating the commercial viability of an integrated oil & gas field development.

  • Academic capstone project
  • Team of 5
  • My role: Economic Analyst
  • Presented to oil & gas industry professionals
Evaluation horizon
20 yrs
Producers compared
15 vs 30
Selected fiscal regime
Gross Split
NPV@10%, Scenario B vs A
+78%

02My role

What did I actually analyze?

Every discipline in the team produced assumptions. My job was to turn all of them into one answer: is this development worth the capital it needs — and in which form?

  • Reservoir Engineering

    Oil in place, recovery, scenario design

  • Production Engineering

    Well performance, artificial lift

  • Drilling

    Well design and drilling cost basis

  • Facilities

    Separation, storage, flowline network

  • Commercial Strategy

    Fiscal terms and investment criteria

Economic analyst

Economic decision support

Cost, fiscal terms, cashflow and risk in one model

  • Development scenario

  • Fiscal framework

  • Investment recommendation

Full economics scope

01 · Inputs

What will the field produce, and when?

  • Production & development assumptions
  • Timing of value from production
  • Development scenario evaluation

02 · Cost

What does it take to build and run?

  • CAPEX analysis
  • OPEX analysis
  • Development budget

03 · Fiscal

How is value shared with the state?

  • Fiscal-system analysis
  • PSC Cost Recovery
  • PSC Gross Split
  • Revenue analysis

04 · Value

Is it worth the capital?

  • Project cashflow
  • NPV · IRR · POT · DPI
  • Value creation
  • Sensitivity analysis
  • Scenario comparison & recommendation

03Field to value

Physical decisions become financial outcomes.

The chain from rock to recommendation. The first four links are produced by the reservoir, drilling, production and facilities work. From cost onwards, the analysis is mine.

  1. Reservoir

    How much oil could be there?

    905.6 MMSTB original oil in place (reservoir simulation model)

    Executive summary, p. 7

  2. Wells

    How many producers, and when?

    15 or 30 producers, drilled in phases 2022–2024

    Tables 4.3–4.4, pp. 33–36

  3. Production

    How much can be recovered?

    Recovery factor 12.9% (A) vs 21.6% (B)

    Table 4.5, p. 38

  4. Facilities

    What must be built to handle it?

    50,000 bbl/d separation, 6.8 km flowline, ESP lift

    Executive summary, p. 7

  5. Economic analyst scope begins

    1. CAPEX & OPEX

      What does it cost to build and run?

      Drilling, flowlines, surface facilities, crew, workover, ESP

      Table 8.2, pp. 70–71

    2. Fiscal terms

      Who takes which share?

      Gross Split: base 43% contractor / 57% government

      Section 8.1, p. 69

    3. Cashflow

      When does money come back?

      20-year horizon, 2019–2039, discounted at 10%

      Sections 4.1.2 & 8.3

    4. NPV · IRR · DPI · POT

      Is the value worth the capital?

      Both scenarios clear the DPI hurdle of 1.6

      Section 8.3, p. 74

    5. Investment decision

      Which development should be backed?

      Scenario B, under Gross Split

      Section 9, pp. 78–79

04Development strategy

Twice the wells. Was it worth twice the capital?

The reservoir and production team proposed two development scales for a 20-year life. My task was to show how the extra scale changes investment, production, cost and value — together.

Scenario A

15

producing wells · Base case + 12 new producers (10 in 2022, 2 in 2023)

Scenario B

30

producing wells · Scenario A + 15 producers (9 in 2023, 6 in 2024)

Producing wellsA15B302.0×
Drilling & completionRelative, from the cost tableAbaselineB2× base2.0×
Surface facilitiesCapacity step, not linearAbaselineB10× base10.0×
Peak oil rateA25,718 bopdB51,573 bopd2.0×
Recovery factorA12.9%B21.6%1.7×
Cumulative oilA116.7 MMSTBB195.6 MMSTB1.7×
NPV @ 10%A12,111B21,5961.8×
Value creationA13,332B23,1761.7×
Pay out timeHigher is slower — barely movedA3.29 yrsB3.36 yrs1.02×

Source: Tables 4.3–4.5 (production), Table 8.2 (cost), Tables 8.3–8.4 (economics). Log scale.

What the ladder says

Doubling the wells doubled drilling spend and needed a ten-times larger surface facility. It also lifted recovery 1.7× and NPV by 78% — while pay out time moved by only 0.07 years. The extra scale paid for itself.

05Cost of development

Where the money goes — and what makes it grow.

The raw cost table mixes units, so the useful question is not the totals but how each cost behaves when the development scales from 15 to 30 wells.

CAPEX

Capital deployment

Fixed

Same in both scenarios, regardless of well count.

  • Exploration investment

    A → Bunchanged

Scales with wells

Grows in step with the number of producers.

  • Drilling & completion

    A → B×2.0

Steps with capacity

Jumps when throughput needs a larger network or plant.

  • Flowline network

    A → B×3.3

  • Surface facilities

    A → B×10.0

OPEX

Keeping the field producing

Fixed

Same in both scenarios, regardless of well count.

  • Crew

    A → Bunchanged

  • Field operations

    A → Bunchanged

Scales with wells

Grows in step with the number of producers.

  • Workover

    A → B×2.0

  • ESP (artificial lift)

    A → B×2.0

Steps with capacity

Jumps when throughput needs a larger network or plant.

  • None in this category

Source: Table 8.2 (Rincian Pengeluaran), pp. 70–71. Bars show the ratio of Scenario B to Scenario A totals on a log scale (1×–10×).

Reading

CAPEX grows in steps; OPEX grows with wells. Drilling, workover and ESP double with the well count, while the flowline network and surface plant jump to a new capacity class.

Exploration, crew and field operations stay fixed — so in the larger development they are carried by roughly 1.7× the recovered oil.

06Fiscal framework

Same barrels. Different contract. Different value.

In Indonesia, production is shared between the contractor and the state. The contract decides when costs come back and how big each share is — so it changes the value of the same field.

Option 1

PSC Cost Recovery

  1. 1Gross revenue
  2. 2Contractor recovers eligible costs first
  3. 3Remaining profit is split

Conceptual widths. Split after cost recovery: contractor 15% / government 85% for oil. Strength: faster recovery of capital spent.

Option 2 · selected

PSC Gross Split

  1. 1Gross production
  2. 2Split immediately
  3. 3Contractor funds all costs from its share

Base split, adjusted by variable components (block status, field location, reservoir depth, infrastructure…) and progressive components (local content, production phase, oil price). The contractor funds all costs from its share.

The evidence

At the end of the 20-year horizon, Gross Split left the contractor with roughly 2–3× the discounted cashflow of Cost Recovery, in both scenarios.

  • Gives the contractor a larger share of production to fund development.
  • Simpler to administer than cost recovery.
  • With high, sustained production and a stable oil price, the larger share outweighs cost recovery's faster capital payback.

Scenario A

≈2.2×

Cost Recovery~5,500
Gross Split~12,350

Scenario B

≈2.8×

Cost Recovery~7,500
Gross Split~21,200

Approx. — read from report chartSource: Figures 8.3 and 8.5 (PSC vs Gross Split discounted 10% cashflow), pp. 72–73. Contractor cumulative discounted cashflow at 2039.

07Cashflow

Production and price in. Cost and state share out. What is left is value.

Each year of the 20-year life (2019–2039) becomes one line of cashflow. Discounting those lines at 10% turns a production profile into a single present value.

  1. Productionbarrels per year
  2. Oil priceper barrel
  3. Revenuegross value
  4. Government sharefiscal split
  5. OPEXrunning cost
  6. CAPEXinvestment
  7. Contractor cashflowper year

The shape of the investment

Both scenarios spend first — wells, flowlines and facilities — and only then earn. The curve bottoms out during build-out and turns positive once the new wells are on stream.

A · pay out
3.29yrs
B · pay out
3.36yrs

B spends more before it earns, then climbs faster and ends 1.8× higher.

Cumulative discounted cashflow, Scenario A and BCumulative discounted contractor cashflow under Gross Split, 2019 to 2039. Both scenarios start negative while wells and facilities are built, turn positive in 2023 (A) and 2024 (B), and end near the reported NPV at 10%: 12,111.14 for A and 21,595.53 for B.05k10k15k20k201920232027203120352039BUILD-OUTA ≈ 12,350B ≈ 21,200
Cumulative discounted contractor cashflow under Gross Split, 2019 to 2039. Both scenarios start negative while wells and facilities are built, turn positive in 2023 (A) and 2024 (B), and end near the reported NPV at 10%: 12,111.14 for A and 21,595.53 for B.

Approx. — read from report chartSource: Figures 8.3 and 8.5, pp. 72–73. Contractor, Gross Split, 10% discount rate; end values match the reported NPV.

08Economic performance

Both scenarios pass. One creates far more value.

I read the five indicators together rather than chasing one number. Each answers a different investor question: how much, how fast, how efficient.

NPV @ 10%

Present value of all future contractor cashflows, discounted at 10%.

A12,111

B21,596

B +78%

Value creation

Value added to the company by the development strategy.

A13,332

B23,176

B +74%

IRR

Discount rate at which the project's NPV becomes zero.

A52%

B57%

B +5 pts

DPI

Discounted profitability index: discounted net return per unit of discounted investment.

A6.95

B9.20

B +32%

Pay out time

Pay out time: years until cumulative cashflow recovers the investment.

A3.29 yrs

B3.36 yrs

Near tie: B pays back 0.07 yrs later

Source: Tables 8.3 and 8.4, p. 74. NPV and Value Creation are shown as reported by the project economic model (contractor, Gross Split, 10% discount rate).

Interpretation

Four of five indicators favour B by a clear margin; the fifth, pay out time, is effectively a tie. That consistency — not one large NPV — is what made the recommendation robust.

09Sensitivity

Revenue decides. Cost only adjusts.

Which assumption could break the case? I flexed each input by 30% up and down and watched the contractor NPV.

Revenue

Production volume × oil price

-47.7%+47.7%NPV changes between -47.7% and +47.7%.

Cost driver

CAPEX / OPEX (larger effect)

-15.4%+15.4%NPV changes between -15.4% and +15.4%.

Cost driver

CAPEX / OPEX (smaller effect)

-2.3%+2.3%NPV changes between -2.3% and +2.3%.

Source: Spider analysis, contractor NPV, Gross Split (Section 8.4, pp. 76–77). The chart legend in the report is cropped, so the two cost lines are shown together as CAPEX / OPEX.

±48%

NPV swing from a 30% change in revenue — price or volume.

≤ ±15%

Largest swing from the same change in a cost line.

Every tested case stays NPV-positive.

The economic risk sits in production delivery and oil price, not in cost overruns — so that is where monitoring and contingency should focus.

10Decision

Develop the larger field. Under Gross Split.

The technical case said Scenario B recovers the most oil. The economic case had to show that the extra wells, flowlines and plant would repay themselves — and under which contract. Both answers pointed the same way.

Scenario B · 30 producers

Selected development

Scenario B — 30 producers

  • NPV@10% 21,595.53 vs 12,111.14: +78% more value.
  • DPI 9.20 vs 6.95 — both far above the 1.6 hurdle, B clearly higher.
  • IRR 57% vs 52%, while pay out time moves only from 3.29 to 3.36 years.
  • Highest recovery factor (21.6%), supported by the technical team's scenario analysis.

Selected economic framework

PSC Gross Split

  • Gives the contractor a larger share of production to fund development.
  • Simpler to administer than cost recovery.
  • With high, sustained production and a stable oil price, the larger share outweighs cost recovery's faster capital payback.

Source: Sections 8.3 and 9, pp. 73–79.

Technical potential becomes investment value only when someone can show the numbers behind it.